Motol University Hospital – B Wing

In July all main substations and substations on individual floors were delivered and connected. At the same time, assembly of end elements on individual floors was carried out as well as activation of the KNX system on the first two floors.

Assembly and activation of individual floors is underway. Revision and inspection by the Technical Inspection of the Czech Republic will take place in August.